Material Cost Estimate for Construction of a 10 Cubic Meter Fixed Dome Biogas Plant


 

The following comprises of materials and equipment cost estimates for the construction of a 10 cubic meter Fixed Dome Biogas Plant:

Cement (24), Sand (7), Ballast (4), Stones (400), Water Proof Cement (4), R6 (1), Waste Pipe 4” (1), Gi Pipe 1” (1), Bricks (400), Binding Wire (1), Paint Brush 6” (1),   Dome Pipe  (1)


Material and Equipment Cost Estimates for a 10 Cubic Meter Fixed Dome Biogas Plant

MATERIAL QUANTITY UNIT COST
(KES)
CEMENT 24 BAGS 21,120
SAND 7 TONNES 14,000
QUARRY DUST 3 TONNES 7,000
BALLAST 4 TONNES 8,000
STONES 400 FEET 14,000
BRICKS 400 PCS 4,000
WATERPROOF CEMENT DOC FIXED 5 KGS 1,000
R 6 1 PCS 600
WASTE PIPE 4” 1 FEET 1,500
GI PIPE 1” 1 1 1,500
DOME PIPE 1 SET 5,000
BINDING WIRE 1 KGS 300
PLYWOOD 2 SHEETS 1,200
NAILS 2 KGS 240
PIPING & FITTINGS 10,000
BIOGAS DOUBLE BURNER 1 PCS 8,000
FILTER 1 PCS 12,500
PPR PIPES (3/4) 1 ROLL 6,500
SUB-TOTAL  116,460
LABOR CHARGES     60,000
SUM TOTAL 176,460

 

TERMS:

  • Material Cost: Client to meet total cost (100%) to facilitate procurement
  • Technical Labour: (70% commitment) | 30% to be paid upon completion of the plant
  • Duration: Approximately. One and half weeks

For inquiries about Biogas Plant installation at institutional and household levels, kindly contact Kenpro Biogas Program Team or call us +254725788400