Material Cost Estimate for Construction of a 10 Cubic Meter Fixed Dome Biogas Plant


 

The following comprises of materials and equipment cost estimates for the construction of a 10 cubic meter Fixed Dome Biogas Plant:

Cement (24), Sand (7), Ballast (4), Stones (400), Water Proof Cement (4), R6 (1), Waste Pipe 4” (1), Gi Pipe 1” (1), Bricks (400), Binding Wire (1), Paint Brush 6” (1),   Dome Pipe  (1)


Material and Equipment Cost Estimates for a 10 Cubic Meter Fixed Dome Biogas Plant

MATERIAL QUANTITY UNIT OF MEASUREMENT
COST (KES)
CEMENT 24 BAGS 14,400
SAND 7 TONNES 14,000
BALLAST 4 TONNES 8,000
STONES 400 FEET 14,000
WATER PROOF CEMENT 4 KGS 1,000
R6 1 PCS 900
WASTE PIPE 4” 1 FEET 1,000
GI PIPE 1” 1 1 1,500
BRICKS 400 PCS 4,000
BINDING WIRE 1 KGS 300
PAINT BRUSH 6” 1 PCS 150
DOME PIPE 1 PCS 4,000
DOUBLE BURNER 1 PCS 7,500
LABOUR CHARGE 60,000
TOTAL 130,750

Terms:

    • Labor Charge: Inclusive technical labour
    • DIGESTER HOLE: Client to excavate the digester based on the dimensions provisions
    • PIPING: Biogas piping and fittings costs estimated after biogas installation
    • BRICKS: Molded at the site